  319.015.  Definitions. — For the purposes of sections 319.010 to 319.050, the following terms mean:

  (1) "Approximate location", a strip of land not wider than the width of the underground facility plus two feet on either side thereof. In situations where reinforced concrete, multiplicity of adjacent facilities or other unusual specified conditions interfere with location attempts, the owner or operator shall designate to the best of his or her ability an approximate location of greater width;

  (2) "Excavation", any operation in which earth, rock or other material in or on the ground is moved, removed or otherwise displaced by means of any tools, equipment or explosives and includes, without limitation, backfilling, grading, trenching, digging, ditching, drilling, well-drilling, augering, boring, tunneling, scraping, cable or pipe plowing, plowing-in, pulling-in, ripping, driving, and demolition of structures, except that, the use of mechanized tools and equipment to break and remove pavement and masonry down only to the depth of such pavement or masonry, the use of high-velocity air to disintegrate and suction to remove earth, rock and other materials, and the tilling of soil for agricultural or seeding purposes shall not be deemed excavation. Backfilling or moving earth on the ground in connection with other excavation operations at the same site shall not be deemed separate instances of excavation;

  (3) "Marking", the use of stakes, paint or other clearly identifiable materials to show the field location of underground facilities, or the area of proposed excavation, in accordance with the color code standard of the American Public Works Association. Unless otherwise provided by the American Public Works Association, the following color scheme shall be used: blue for potable water; purple for reclaimed water, irrigation and slurry lines; green for sewers and drain lines; red for electric, power lines, cables, conduit and lighting cables; orange for communications, including telephone, cable television, alarm or signal lines, cable or conduit; yellow for gas, oil, steam, petroleum or gaseous materials; white for proposed excavation; pink for temporary marking of construction project site features such as centerline and top of slope and toe of slope;

  (4) "Notification center", a statewide organization operating twenty-four hours a day, three hundred sixty-five days a year on a not-for-profit basis, supported by its participants, or by more than one operator of underground facilities, having as its principal purpose the statewide receipt and dissemination to participating owners and operators of underground facilities of information concerning intended excavation activities in the area where such owners and operators have underground facilities, and open to participation by any and all such owners and operators on a fair and uniform basis. Such notification center shall be governed by a board of directors elected by the membership and composed of representatives from each general membership group;

  (5) "Permitted project", a project for which a permit for the work to be performed is required to be issued by a local, state or federal agency and, as a prerequisite to receiving such permit, the applicant is required to locate all underground facilities in the area of the work and in the vicinity of the excavation and is required to notify each owner of such underground facilities;

  (6) "Person", any individual, firm, joint venture, partnership, corporation, association, cooperative, municipality, political subdivision, governmental unit, department or agency and shall include a notification center and any trustee, receiver, assignee or personal representative thereof;

  (7) "Pipeline facility" includes, without limitation, new and existing pipe, rights-of-way, and any equipment, facility, or building used or intended for use in the transportation of gas or the treatment of gas, or used or intended for use in the transportation of hazardous liquids including petroleum, or petroleum products;

  (8) "Preengineered project", a project which is approved by an agency or political subdivision of the state and for which the agency or political subdivision responsible for the project, as part of its engineering and contract procedures, holds a meeting prior to the commencement of any construction work on such project and in such meeting all persons determined by the agency or political subdivision to have underground facilities located within the excavation area of the project are invited to attend and given an opportunity to verify or inform any agency or political subdivision of the location of their underground facilities, if any, within the excavation area and where the location of all known underground facilities are duly located or noted on the engineering drawing as specifications for the project;

  (9) "Residential property", any real estate used or intended to be used as a residence by not more than four families on which no underground facilities exist which are owned or operated by any party other than the owner of said property;

  (10) "Underground facility", any item of personal property which shall be buried or placed below ground for use in connection with the storage or conveyance of water, storm drainage, sewage, telecommunications service, cable television service, electricity, oil, gas, hazardous liquids or other substances, and shall include but not be limited to pipes, sewers, conduits, cables, valves, lines, wires, manholes, attachments and those portions of pylons or other supports below ground that are within any public or private street, road or alley, right-of-way dedicated to the public use or utility easement of record, or prescriptive easement; except that where gas distribution lines or electric lines, telecommunications facilities, cable television facilities, water service lines, water system, storm drainage or sewer system lines are and such lines or facilities are owned solely by the owner or owners of such property, such lines or facilities receiving service shall not be considered underground facilities for purposes of this chapter; provided, however, for railroads regulated by the Federal Railroad Administration, "underground facility" as used in sections 319.015 to 319.050 shall not include any excavating done by a railroad when such excavating is done entirely on land which the railroad owns or on which the railroad operates, or in the event of emergency, on adjacent land;

  (11) "Working day", every day, except Saturday, Sunday or a legally declared local, state or federal holiday.

­­--------

(L. 1976 S.B. 583 § 2, A.L. 1991 S.B. 214 & 264, A.L. 2001 H.B. 425)


---- end of effective  28 Aug 2001 ----

use this link to bookmark section  319.015


 - All versions
Effective End
319.015 1/1/2015
319.015 1/1/2009 1/1/2015
319.015 8/28/2001 1/1/2009

Click here for the Reorganization Act of 1974 - or - Concurrent Resolutions Having Force & Effect of Law
In accordance with Section 3.090, the language of statutory sections enacted during a legislative session are updated and available on this website on the effective date of such enacted statutory section. Revisor Home    

Other Information
 Recent Sections Editorials May Be Cited As Tables & Forms Multiple Enact
Repeal & Transfer Definitions End Report

Site changes Pictures Contact

Other Links
Legislative Research Oversight MOLIS
Library MO WebMasters
Senate
Missouri Senate
State of Missouri
MO.gov
House
Missouri House