  444.770.  Permit required, when —r elease of certain bonds. — 1. It shall be unlawful for any operator to engage in surface mining without first obtaining from the commission a permit to do so, in such form as is hereinafter provided, including any operator involved in any gravel mining operation where the annual tonnage of gravel mined by such operator is less than five thousand tons.

  2. Sections 444.760 to 444.790 shall apply only to those areas which are opened on or after January 1, 1972, or to the extended portion of affected areas extended after that date. The effective date of this section for minerals not previously covered under the provisions of sections 444.760 to 444.790 shall be August 28, 1990.

  3. All surface mining operations where land is affected after September 28, 1971, which are under the control of any government agency whose regulations are equal to or greater than those imposed by section 444.774, are not subject to the further provisions of sections 444.760 to 444.790, except that such operations shall be registered with the land reclamation commission.

  4. Any portion of a surface mining operation which is subject to the provisions of sections 260.200 to 260.245, RSMo, and the regulations promulgated thereunder, shall not be subject to the provisions of sections 444.760 to 444.790, and any bonds or portions thereof applicable to such operations shall be promptly released by the commission, and the associated permits canceled by the commission upon presentation to it of satisfactory evidence that the operator has received a permit pursuant to section 260.205, RSMo, and the regulations promulgated thereunder. Any land reclamation bond associated with such released permits shall be retained by the commission until presentation to the commission of satisfactory evidence that:

  (1) The operator has complied with sections 260.226 and 260.227, RSMo, and the regulations promulgated thereunder, pertaining to closure and postclosure plans and financial assurance instruments; and

  (2) The operator has commenced operation of the solid waste disposal area or sanitary landfill as those terms are defined in chapter 260, RSMo.

  5. Notwithstanding the provisions of subsection 1 of this section, any political subdivision which uses its own personnel and equipment or any private individual for personal use may conduct in-stream gravel operations without obtaining from the commission a permit to conduct such an activity.

­­--------

(L. 1971 H.B. 519 § 5, A.L. 1990 H.B. 1584, A.L. 2001 H.B. 453)


---- end of effective  28 Aug 2001 ----

use this link to bookmark section  444.770


 - All versions
Effective End
444.770 8/28/2014
444.770 8/28/2009 8/28/2014
444.770 8/28/2001 8/28/2009

Click here for the Reorganization Act of 1974 - or - Concurrent Resolutions Having Force & Effect of Law
In accordance with Section 3.090, the language of statutory sections enacted during a legislative session are updated and available on this website on the effective date of such enacted statutory section. Revisor Home    

Other Information
 Recent Sections Editorials May Be Cited As Tables & Forms Multiple Enact
Repeal & Transfer Definitions End Report

Site changes Pictures Contact

Other Links
Legislative Research Oversight MOLIS
Library MO WebMasters
Senate
Missouri Senate
State of Missouri
MO.gov
House
Missouri House